X52 PSL2 ERW Steel Pipe in Malaysia
Sources: this site    Click:     Date: 2015-12-13 1:48:39
			   | Order Production Schedule | |||
| Our Order No. | 20151101 | ||
| Client's Order No. | ABE-02565376 | ||
| Desription of Order | API 5L X52 PSL2 ERW Steel Pipe in Malaysia (880 MT) 14" / 24"*SCH80 | ||
| Process steps | From date | To date | Delivery Time | 
| Proforma invoice signed | 2015-10-01 | 2015-10-01 | - | 
| Down payment received date | 2015-10-3 | 2015-10-3 | - | 
| Feed materials purchasing date | 2015-10-4 | 2015-10-15 | 12days | 
| Start production | 2015-10-16 | 2015-10-31 | 16days | 
| Technical operation | 2015-11-01 | 2015-11-4 | 4days | 
| Pipe end, marking | 2015-11-05 | 2015-11-07 | 3days | 
| The third party inspection | 2015-11-08 | 2015-11-10 | 3 days | 
| Total | 40 days | ||